Hotel Renovation with Rapid Liquid Screed – Buckinghamshire
A luxury hotel in Buckinghamshire required a fast-turnaround screed installation to meet renovation deadlines. Flooring needed to be ready within 24 hours.

Project Overview:
-
Location: Buckinghamshire
-
Sector: Hospitality
-
Screed Type: Fast-drying liquid screed
-
Area: 400m²
-
Timeframe: Completed in 2 days
Our Approach:
We installed a rapid-drying liquid screed to speed up the renovation process. Our team ensured precise levelling and laitance removal for a perfect finish.
Results:
The floor was ready for flooring installation within 24 hours, keeping the project firmly on schedule.