Hotel Renovation with Rapid Liquid Screed – Buckinghamshire

A luxury hotel in Buckinghamshire required a fast-turnaround screed installation to meet renovation deadlines. Flooring needed to be ready within 24 hours.

Project Overview:

  • Location: Buckinghamshire

  • Sector: Hospitality

  • Screed Type: Fast-drying liquid screed

  • Area: 400m²

  • Timeframe: Completed in 2 days

Our Approach:

We installed a rapid-drying liquid screed to speed up the renovation process. Our team ensured precise levelling and laitance removal for a perfect finish.

Results:

The floor was ready for flooring installation within 24 hours, keeping the project firmly on schedule.